ENPRODE’s Responsibilities;
» Feasibility Report
» Conceptual Design
» Basic and Detailed Engineering
Detailed Work;
» By-pass Stack & Diverter;
» Demineralized Water Plant; Ongoing Project
» Boiler Feed Water System;
» Compressed Air System;
» Natural Gas RMS-A Station;
» Natural Gas Simplex Filter;
» Heating Ventilation and Air Conditioning (HVAC);
» Fire Protection system, Fire Hydrant and Stand Pipe System;
» 154 kV Air Insulated Switchyard;
» Step-up and Service Transformers;
» 11 kV Circuit Breakers;
» 0.4 kV Distribution Panels;
» 0.4 kV Motor Control Centers (MCCs);
» Battery Chargers, Batteries and DC Distribution Board;
» 0.4 kV Uninterruptible Power Supply (UPS) System and AC Distribution Board;
» Continuous Emission Monitoring System (CEMS).
The plant is designed and configured to achieve the utmost possible output efficiency by
utilizing the waste heat in compliance with all environmental requirements. All other associated
equipment, ancillaries and Auxiliary Systems are complementary for obtaining maximum
Reliable, Available and Maintainable Operation Standards.
The common structures associated major equipment’s auxiliary services and underground
facilities are to be designed and built in a manner to comply with the applicable laws and relevant
legislation of Turkey and considering the latest techniques and standards applicable in the
international practices of the power generation industry.