AGE CCPP ENPRODE’s Project Responsibilities;
Natural Gas » EPCM- Engineering, Procurement and Construction Management
» Bankable and Technical Feasibility Study
Fired CCPP » Conceptual, Basic and Detailed Engineering & Design
» Procurement Consulting
» Construction Management
» Commissioning and Start-up
(200 MW, 3 x AGE signed an agreement with ENPRODE Engineering in June 2010 for
SIEMENS SGT800 the Design, Engineering, Procurement and Construction Management
GTG + l x STG) (EPCM) of all project phases from the conceptual design up to
commercial start-up of their 200 MW Combined Cycle Power Plant
investment.
The Power Plant was constructed on land owned by AGE located in
Sarayköy, which is a town 22 km to Denizli. The Plant configuration
comprises; 3+1 Gas Turbine Combined Cycle technology and consists
of three Gas Turbines, Heat Recovery Steam Generators (HRSG), one
Steam Turbine and one Air Cooled Condenser (ACC) in accordance
with the equipment performance. AGE CCPP was put into commercial
Owner: operation in Simple Cycle mode on 27 July 2012 upon Ministerial
Acceptance
AGE DENİZLİ Natural Gas and
Electricity Production Inc.
Project Location:
Denizli, Turkey
32